Construction
Construction Timeline
Follow along with our construction timeline to stay up-to-date on our brand-new, cottage-style apartments near Binghamton University! Contact our leasing team today for more information.
Phase 1 – Mar 2025 – Jan 2026
Phase 1 of the construction process is defined by site prep and foundational work. By January 2026, the construction team will have completed the concrete foundation and framing for all cottages in the community. The MEP, drywall, door, trim, countertop, and permanent power installation phases will also have commenced.
Phase 2 – Jan 2026 – Aug 2026
We’re excited to welcome you! Hard hat tours of our student cottages are expected to take place in Spring 2026. Once final touches, repairs, and quality checks are made, our knowledgeable leasing team will assist residents with the transition into their new home!
Contact Us- 2025Spring
Construction Site Prep
Site is prepped for construction to begin.
- 2025June
Foundation Work Begins
Foundation work begins to prepare for concrete slabs to be poured. These concrete slabs will serve as the foundations for the cottages. These begin in the front left section of the community, working towards the back right.
- 2025July
Utility Work & Retaining Walls
Concrete pours continue, in conjunction with utility work on site. Retaining walls are started.
- 2025August
Clubhouse Foundation Work Begins
Foundation work begins for the Clubhouse and is completed for the cottages near the front middle of the community.
- 2025September
Front Cottage Framing Begins
Framing begins for cottages near the front of the community and concrete foundations are completed for the next phase.
- 2025October
Framing Continues & MEP Installation Begins
Framing begins for the cottages near the back of the community. Begin mechanical, electrical, and plumbing (“MEP”) installation for the cottages in the front of the community. After MEP installation is completed in this section, begin drywall installation, painting, doors installation, & trim installation. Complete clubhouse concrete foundation.
- 2025November
Drywall, MEP, & Painting Next Phase
Begin the next phase of MEP, drywall installation, painting, door installation, and trim installation. The clubhouse is topped out. The next phase of concrete foundations are completed.
- 2025December
Foundation & Framing Final Phases
Complete the final phase of concrete foundations. Complete framing for final phases. All structures are topped out. Begin cabinet and countertop installation.
- 2026January
Permanent Power Installation Begins
Begin MEP, drywall installation, painting, door installation, and trim installation for the final phase of cottages. Permanent power installation begins at the front of the community.
- 2026February
Cabinet & Countertop Installation Completed
Permanent power installation work continues for the cottages near the back of the community. Clubhouse MEP, drywall installation, painting, door installation, & trim installation is completed. Complete cabinet and countertop installation in the final phase of the community.
- 2026Spring
Hard Hat Tours Begin
Hard hat tours of the community are expected to begin.
- 2026March
Site Work Completed
Site work completed on whole site. Clubhouse permanent power installation will be completed.
- 2026April
Permanent Power Installation Completed
Complete final phase of drywall, paint, doors, & trim. Complete permanent power installation on cottages in the final phase.
- 2026May
Clubhouse Completed
Clubhouse is completed.
- 2026June
TV, Internet, & Cameras Installed
Install TV, Internet, WiFi network, and security cameras. Begin furniture assembly and installation.
- 2026July
Final Repairs & Touch-Ups
The team will be wrapping up, making final repairs and completing any necessary touch-ups. The Community Manager and leasing team will move into the Clubhouse and learn all of the operational equipment.
- 2026August
Move-In Day
Move-In Day. Quality checks will be completed, and residents will begin moving into their brand-new cottage on August 14th.